This open house was active from Oct. 8-24, 2021. Information on this website may no longer be current. Email us for more information.

 

We will collect comments and questions via this open house until Oct. 24. The project team will respond to questions directly.

A summary of comments and responses to questions will be available on the project webpage in the coming weeks.

We will present the bike and pedestrian alternatives to the Board of County Commissioners. We expect the Board will provide guidance on bike and pedestrian options.

The right-of-way acquisition process will begin in the final phase of design. A right-of-way agent will notify and individually work with each impacted property owner to obtain necessary right-of-way and/or easements.

Construction is planned for spring 2023 through fall 2024.

 
  • Surveys and studies

    Fall 2020-Spring 2022
  • First open house

    Oct. 8-24, 2021

    You are here.

  • 30% design milestone

    Summer 2021-spring 2022
  • 75% design milestone

    Spring-summer 2022
  • Second open house

    Summer 2022
  • Final design

    Summer 2022-spring 2023
  • Right-of-way acquisition process

    Summer 2022-spring 2023
  • Contractor bids

    Spring 2023
  • Construction kickoff

    Spring 2023
  • Construction

    Spring 2023-fall 2024
  • Road closure for culvert replacement

    July-August 2023